The addition of utility-scale photo voltaic capability is anticipated to set a brand new report by including 15.4 GW of capability to the US grid in 2021, the US Power Info Administration (EIA) announced today.

Photo voltaic leads the 2021 pack with 39% of complete new US electrical energy producing capability. It’s adopted by wind (31%, or 12.2 GW), pure fuel (16%, or 6.6 GW), battery storage (11%, or 4.3 GW), nuclear (3%, or 1.1 GW), and Different, at 0.2 GW.

Photo voltaic

2021’s anticipated 15.4 GW of photo voltaic will exceed 2020’s almost 12 GW improve, based mostly on reported additions via October (6 GW) and scheduled additions for the final two months of 2020 (5.7 GW).

4 states might be dwelling to greater than half of the brand new utility-scale photo voltaic photovoltaic capability: Texas (28%), Nevada (9%), California (9%), and North Carolina (7%).

As Electrek beforehand reported, Texas will host the largest solar project in the US, the Samson Photo voltaic Power Middle, which might be constructed in 5 phases over the subsequent three years, with every part commencing operation upon completion in 2023.

Wind

One other 12.2 GW of wind capability is scheduled to return on-line in 2021. Final 12 months, 21 GW of wind got here on-line.

Texas and Oklahoma account for greater than half of the 2021 wind capability additions. The 12-MW Coastal Virginia Offshore Wind (CVOW) pilot mission, situated 27 miles off the coast of Virginia Seashore, can also be scheduled to start out industrial operation in early 2021.

Pure fuel

Pure fuel is a unclean fossil gas. Deliberate pure fuel capability additions are reported at 6.6 GW, primarily in Texas, Ohio, and Pennsylvania.

Battery storage

EIA expects the capability of utility-scale battery storage to greater than quadruple; 4.3 GW of battery energy capability additions are anticipated to return on-line by the tip of 2021. It’s because battery storage goes hand-in-hand with inexperienced vitality.

The world’s largest solar-powered battery (409 MW) is below building at Manatee Photo voltaic Power Middle in Florida; the battery is scheduled to be operational by late 2021.

 Within the annual survey, EIA asks respondents to offer deliberate on-line dates for mills coming on-line within the subsequent 5 years. The month-to-month survey tracks the standing of mills coming on-line within the coming 12 months based mostly on reported in-service dates.